description: "Configure the inspection workflow per stage. Roles use the general term with the construction party — RFI Initiator (Contractor), Maker QC (Contractor QC), Checker (PMC), Approver L1-L3 (Site Engineer/PMC Manager/Client). 20 combinations, with worked examples and a decision guide to pick one."
url: https://help.digiqc.com/en/articles/175-2213-digiqc-inspection-workflows
collection: "2.2 Inspect"
updated: 2026-11-05
language: en
---

# 2.2.13 digiQC Inspection Workflows

Configure the inspection workflow per stage. Roles use the general term with the construction party — RFI Initiator (Contractor), Maker QC (Contractor QC), Checker (PMC), Approver L1-L3 (Site Engineer/PMC Manager/Client). 20 combinations, with worked examples and a decision guide to pick one.

### Overview

digiQC lets you **configure the inspection workflow for each stage** to match your organisation's quality process. A workflow decides **who is involved and in what order** — whether the RFI Initiator raises an **RFI** first, whether that RFI needs an **internal check**, what happens on a **Redo** (the **Re-RFI** setting), and **how many sign-offs** (up to 3) are needed. Every stage can use a **different** workflow. There are **20 combinations** in all — this guide helps you pick the one that matches your project.

### What these terms mean on a real project

This guide uses four terms to explain a workflow in construction language. They are not roles in digiQC:

<table style="min-width: 50px;"><colgroup><col style="min-width: 25px;"><col style="min-width: 25px;"></colgroup><tbody><tr><th colspan="1" rowspan="1"><p>Term used in this guide</p></th><th colspan="1" rowspan="1"><p>On a construction project (specific)</p></th></tr><tr><td colspan="1" rowspan="1"><p>RFI Initiator</p></td><td colspan="1" rowspan="1"><p>Contractor's engineer — raises the RFI when the work is ready</p></td></tr><tr><td colspan="1" rowspan="1"><p>Maker QC</p></td><td colspan="1" rowspan="1"><p><strong>Contractor's own QC team</strong> — clears the RFI internally before the Checker is called</p></td></tr><tr><td colspan="1" rowspan="1"><p>Checker</p></td><td colspan="1" rowspan="1"><p><strong>PMC</strong> (or the Client's QC engineer) — physically inspects the work against the checklist</p></td></tr><tr><td colspan="1" rowspan="1"><p>Approver (L1 / L2 / L3)</p></td><td colspan="1" rowspan="1"><p><strong>Senior sign-off</strong> — e.g. Site Engineer, PMC Manager, then Client (up to 3 levels)</p></td></tr></tbody></table>

Throughout this guide the flows use the term with the construction party in brackets — e.g. RFI Initiator (Contractor), Checker (PMC), Approver (Client).

### 🧭 How to use

### The building blocks of a workflow

-   **Stage context** — a workflow applies to **one stage** (e.g. Pre / During / Post). Each stage can have its own workflow. Completing a stage **unlocks the next**; the final stage completes the inspection.
    
-   **RFI** — a Request for Inspection the RFI Initiator (the Contractor, or whichever team/user is set to raise it) raises to signal work is ready. Some workflows have no RFI (the Checker inspects directly).
    
-   **RFI Approval (Maker QC)** — an optional internal check: the **Maker QC (Contractor's QC)** accepts the RFI **before** the Checker (PMC) is called.
    
-   **Approval levels** — after the inspection passes, up to **3 sequential sign-offs** — **Approver L1 → L2 → L3** (e.g. Site Engineer → PMC Manager → Client).
    
-   **Re-RFI (Off / On)** — decides what a **Redo** does once inspection has started: **Off** = back to the **checklist stage** (Checker re-inspects, no fresh RFI); **On** = the RFI Initiator **must raise a fresh RFI** first.
    

### Global rules (apply to every workflow)

1.  **What a Redo or rejection restarts from depends on the stage and the Re-RFI setting:**
    

\- If **Re-RFI is On**, a Redo requires the RFI Initiator **to raise a fresh RFI.** - If **Re-RFI is Off**, a Redo goes back to the **checklist stage** (it has already started) — the **Checker re-inspects, no fresh RFI.** - If the **RFI itself is rejected** (before the checklist stage has started), you **start again from the RFI** — a fresh RFI — whatever the Re-RFI setting, because inspection never began.

1.  **An inspection fail re-inspects only the failed checkpoints** — but you also have the **option to change other checkpoints** if needed.
    
2.  **The Maker QC RFI check is optional** — if it isn't set up, the RFI goes straight to the Checker.
    
3.  **Completing a stage unlocks the next** (Pre → During → Post); the final stage ends the inspection.
    
4.  **Each stage can use a different workflow.**
    

### How to pick your workflow

Answer four questions and you land on exactly one of the 20:

1.  **Does the RFI Initiator (the Contractor, or the team/user you set) need to formally request inspection?** Yes → an RFI workflow (5–20). No → a No-RFI workflow (1–4).
    
2.  **Should the Maker QC (Contractor's QC) clear the RFI first?** Yes → an "RFI Approval" workflow (9–12, 17–20).
    
3.  **How many sign-offs after the inspection passes?** None, or L1 / L1-L2 / L1-L2-L3.
    
4.  **On a redo, must the RFI Initiator raise a fresh RFI?** Yes → Re-RFI On (13–20). No → Re-RFI Off (5–12).
    

### Real construction examples

#### Small job — Checker inspects directly (Workflow 1)

No RFI, no sign-off. The **Checker (PMC)** inspects the work against the checklist and passes it. **Choose this when** the checker is trusted and you need neither a request step nor a separate approval — e.g. a small project or a low-risk stage.

#### RFI Initiator signals readiness, Checker inspects (Workflow 5)

The **RFI Initiator (Contractor) raises an RFI** when work is ready; the **Checker (PMC) inspects.** No approval afterwards. **Choose this when** the RFI Initiator should formally request the inspection, but a passed inspection is enough on its own.

#### RFI Initiator raises the RFI → Checker inspects → Approver signs off (Workflow 6)

The classic setup. The **RFI Initiator (Contractor) raises the RFI**, the **Checker (PMC) inspects** on site, and the **Approver (Client) gives the final approval (L1).** **Choose this when** the client wants to sign off every passed inspection.

#### RFI Initiator self-certifies first (Workflow 10)

The **RFI Initiator (Contractor) raises the RFI**, the **Maker QC (Contractor's QC) clears it internally**, then the **Checker (PMC) inspects**, and the **Approver (Client) approves (L1).** **Choose this when** the contractor must self-check before calling the PMC — it cuts down wasted PMC site visits.

#### Full chain with three sign-offs (Workflow 8, or 16 for Re-RFI On)

**RFI Initiator (Contractor) raises the RFI → Checker (PMC) inspects → Approver L1 (Site Engineer) → Approver L2 (PMC Manager) → Approver L3 (Client).** **Choose this for** critical or high-value work needing several authorities. Use the **Re-RFI On** version (Workflow 16) when a redo should force the RFI Initiator to raise a **fresh RFI** — maximum accountability.

#### What a Redo looks like on site — Re-RFI Off vs On

Say an approver gives a **Redo** after inspection. With **Re-RFI Off**, the work goes **back to the checklist stage** — the **Checker (PMC)** re-inspects once the RFI Initiator has fixed it, no fresh RFI. With **Re-RFI On**, the **RFI Initiator (Contractor) must raise a fresh RFI** first, formally re-requesting the inspection. (If instead the **RFI was rejected** before inspection ever started, you begin again from the **RFI**.) **Off** is lighter for a trusted contractor; **On** gives a formal paper-trail for high-accountability projects.

### The 20 workflows

They fall into three groups: **No RFI (1–4)** — the Checker inspects directly; **RFI, Re-RFI Off (5–12)** — on Redo the work returns to the checklist stage; **RFI, Re-RFI On (13–20)** — on Redo the RFI Initiator raises a fresh RFI.

<table style="min-width: 150px;"><colgroup><col style="min-width: 25px;"><col style="min-width: 25px;"><col style="min-width: 25px;"><col style="min-width: 25px;"><col style="min-width: 25px;"><col style="min-width: 25px;"></colgroup><tbody><tr><th colspan="1" rowspan="1"><p>#</p></th><th colspan="1" rowspan="1"><p>Workflow</p></th><th colspan="1" rowspan="1"><p>RFI</p></th><th colspan="1" rowspan="1"><p>RFI approval</p></th><th colspan="1" rowspan="1"><p>Re-RFI</p></th><th colspan="1" rowspan="1"><p>Approval levels</p></th></tr><tr><td colspan="1" rowspan="1"><p>1</p></td><td colspan="1" rowspan="1"><p>Inspection</p></td><td colspan="1" rowspan="1"><p>No</p></td><td colspan="1" rowspan="1"><p>No</p></td><td colspan="1" rowspan="1"><p>—</p></td><td colspan="1" rowspan="1"><p>None</p></td></tr><tr><td colspan="1" rowspan="1"><p>2</p></td><td colspan="1" rowspan="1"><p>Inspection → L1</p></td><td colspan="1" rowspan="1"><p>No</p></td><td colspan="1" rowspan="1"><p>No</p></td><td colspan="1" rowspan="1"><p>—</p></td><td colspan="1" rowspan="1"><p>L1</p></td></tr><tr><td colspan="1" rowspan="1"><p>3</p></td><td colspan="1" rowspan="1"><p>Inspection → L1 → L2</p></td><td colspan="1" rowspan="1"><p>No</p></td><td colspan="1" rowspan="1"><p>No</p></td><td colspan="1" rowspan="1"><p>—</p></td><td colspan="1" rowspan="1"><p>L1 L2</p></td></tr><tr><td colspan="1" rowspan="1"><p>4</p></td><td colspan="1" rowspan="1"><p>Inspection → L1 → L2 → L3</p></td><td colspan="1" rowspan="1"><p>No</p></td><td colspan="1" rowspan="1"><p>No</p></td><td colspan="1" rowspan="1"><p>—</p></td><td colspan="1" rowspan="1"><p>L1 L2 L3</p></td></tr><tr><td colspan="1" rowspan="1"><p>5</p></td><td colspan="1" rowspan="1"><p>RFI → Inspection</p></td><td colspan="1" rowspan="1"><p>Yes</p></td><td colspan="1" rowspan="1"><p>No</p></td><td colspan="1" rowspan="1"><p>Off</p></td><td colspan="1" rowspan="1"><p>None</p></td></tr><tr><td colspan="1" rowspan="1"><p>6</p></td><td colspan="1" rowspan="1"><p>RFI → Inspection → L1</p></td><td colspan="1" rowspan="1"><p>Yes</p></td><td colspan="1" rowspan="1"><p>No</p></td><td colspan="1" rowspan="1"><p>Off</p></td><td colspan="1" rowspan="1"><p>L1</p></td></tr><tr><td colspan="1" rowspan="1"><p>7</p></td><td colspan="1" rowspan="1"><p>RFI → Inspection → L1 → L2</p></td><td colspan="1" rowspan="1"><p>Yes</p></td><td colspan="1" rowspan="1"><p>No</p></td><td colspan="1" rowspan="1"><p>Off</p></td><td colspan="1" rowspan="1"><p>L1 L2</p></td></tr><tr><td colspan="1" rowspan="1"><p>8</p></td><td colspan="1" rowspan="1"><p>RFI → Inspection → L1 → L2 → L3</p></td><td colspan="1" rowspan="1"><p>Yes</p></td><td colspan="1" rowspan="1"><p>No</p></td><td colspan="1" rowspan="1"><p>Off</p></td><td colspan="1" rowspan="1"><p>L1 L2 L3</p></td></tr><tr><td colspan="1" rowspan="1"><p>9</p></td><td colspan="1" rowspan="1"><p>RFI → RFI Approval → Inspection</p></td><td colspan="1" rowspan="1"><p>Yes</p></td><td colspan="1" rowspan="1"><p>Yes</p></td><td colspan="1" rowspan="1"><p>Off</p></td><td colspan="1" rowspan="1"><p>None</p></td></tr><tr><td colspan="1" rowspan="1"><p>10</p></td><td colspan="1" rowspan="1"><p>RFI → RFI Approval → Inspection → L1</p></td><td colspan="1" rowspan="1"><p>Yes</p></td><td colspan="1" rowspan="1"><p>Yes</p></td><td colspan="1" rowspan="1"><p>Off</p></td><td colspan="1" rowspan="1"><p>L1</p></td></tr><tr><td colspan="1" rowspan="1"><p>11</p></td><td colspan="1" rowspan="1"><p>RFI → RFI Approval → Inspection → L1 → L2</p></td><td colspan="1" rowspan="1"><p>Yes</p></td><td colspan="1" rowspan="1"><p>Yes</p></td><td colspan="1" rowspan="1"><p>Off</p></td><td colspan="1" rowspan="1"><p>L1 L2</p></td></tr><tr><td colspan="1" rowspan="1"><p>12</p></td><td colspan="1" rowspan="1"><p>RFI → RFI Approval → Inspection → L1 → L2 → L3</p></td><td colspan="1" rowspan="1"><p>Yes</p></td><td colspan="1" rowspan="1"><p>Yes</p></td><td colspan="1" rowspan="1"><p>Off</p></td><td colspan="1" rowspan="1"><p>L1 L2 L3</p></td></tr><tr><td colspan="1" rowspan="1"><p>13</p></td><td colspan="1" rowspan="1"><p>RFI → Inspection (Re-RFI On)</p></td><td colspan="1" rowspan="1"><p>Yes</p></td><td colspan="1" rowspan="1"><p>No</p></td><td colspan="1" rowspan="1"><p>On</p></td><td colspan="1" rowspan="1"><p>None</p></td></tr><tr><td colspan="1" rowspan="1"><p>14</p></td><td colspan="1" rowspan="1"><p>RFI → Inspection → L1 (Re-RFI On)</p></td><td colspan="1" rowspan="1"><p>Yes</p></td><td colspan="1" rowspan="1"><p>No</p></td><td colspan="1" rowspan="1"><p>On</p></td><td colspan="1" rowspan="1"><p>L1</p></td></tr><tr><td colspan="1" rowspan="1"><p>15</p></td><td colspan="1" rowspan="1"><p>RFI → Inspection → L1 → L2 (Re-RFI On)</p></td><td colspan="1" rowspan="1"><p>Yes</p></td><td colspan="1" rowspan="1"><p>No</p></td><td colspan="1" rowspan="1"><p>On</p></td><td colspan="1" rowspan="1"><p>L1 L2</p></td></tr><tr><td colspan="1" rowspan="1"><p>16</p></td><td colspan="1" rowspan="1"><p>RFI → Inspection → L1 → L2 → L3 (Re-RFI On)</p></td><td colspan="1" rowspan="1"><p>Yes</p></td><td colspan="1" rowspan="1"><p>No</p></td><td colspan="1" rowspan="1"><p>On</p></td><td colspan="1" rowspan="1"><p>L1 L2 L3</p></td></tr><tr><td colspan="1" rowspan="1"><p>17</p></td><td colspan="1" rowspan="1"><p>RFI → RFI Approval → Inspection (Re-RFI On)</p></td><td colspan="1" rowspan="1"><p>Yes</p></td><td colspan="1" rowspan="1"><p>Yes</p></td><td colspan="1" rowspan="1"><p>On</p></td><td colspan="1" rowspan="1"><p>None</p></td></tr><tr><td colspan="1" rowspan="1"><p>18</p></td><td colspan="1" rowspan="1"><p>RFI → RFI Approval → Inspection → L1 (Re-RFI On)</p></td><td colspan="1" rowspan="1"><p>Yes</p></td><td colspan="1" rowspan="1"><p>Yes</p></td><td colspan="1" rowspan="1"><p>On</p></td><td colspan="1" rowspan="1"><p>L1</p></td></tr><tr><td colspan="1" rowspan="1"><p>19</p></td><td colspan="1" rowspan="1"><p>RFI → RFI Approval → Inspection → L1 → L2 (Re-RFI On)</p></td><td colspan="1" rowspan="1"><p>Yes</p></td><td colspan="1" rowspan="1"><p>Yes</p></td><td colspan="1" rowspan="1"><p>On</p></td><td colspan="1" rowspan="1"><p>L1 L2</p></td></tr><tr><td colspan="1" rowspan="1"><p>20</p></td><td colspan="1" rowspan="1"><p>RFI → RFI Approval → Inspection → L1 → L2 → L3 (Re-RFI On)</p></td><td colspan="1" rowspan="1"><p>Yes</p></td><td colspan="1" rowspan="1"><p>Yes</p></td><td colspan="1" rowspan="1"><p>On</p></td><td colspan="1" rowspan="1"><p>L1 L2 L3</p></td></tr></tbody></table>

### Re-RFI Off vs Re-RFI On

<table style="min-width: 75px;"><colgroup><col style="min-width: 25px;"><col style="min-width: 25px;"><col style="min-width: 25px;"></colgroup><tbody><tr><th colspan="1" rowspan="1"><p>Scenario</p></th><th colspan="1" rowspan="1"><p>Re-RFI Off</p></th><th colspan="1" rowspan="1"><p>Re-RFI On</p></th></tr><tr><td colspan="1" rowspan="1"><p>Approver gives Redo (after inspection)</p></td><td colspan="1" rowspan="1"><p>Back to the checklist stage — Checker (PMC) re-inspects, no fresh RFI</p></td><td colspan="1" rowspan="1"><p>RFI Initiator (Contractor) must raise a fresh RFI</p></td></tr><tr><td colspan="1" rowspan="1"><p>RFI rejected before inspection starts</p></td><td colspan="1" rowspan="1"><p>Start again from the RFI (fresh RFI)</p></td><td colspan="1" rowspan="1"><p>Start again from the RFI (fresh RFI)</p></td></tr><tr><td colspan="1" rowspan="1"><p>Inspection fails</p></td><td colspan="1" rowspan="1"><p>Re-inspect the failed checkpoints (option to change others)</p></td><td colspan="1" rowspan="1"><p>Re-inspect the failed checkpoints (option to change others)</p></td></tr><tr><td colspan="1" rowspan="1"><p>Who controls re-inspection</p></td><td colspan="1" rowspan="1"><p>Checker (PMC)</p></td><td colspan="1" rowspan="1"><p>RFI Initiator (Contractor) formally re-requests</p></td></tr><tr><td colspan="1" rowspan="1"><p>Best for</p></td><td colspan="1" rowspan="1"><p>Projects with a trusted contractor</p></td><td colspan="1" rowspan="1"><p>High-accountability projects</p></td></tr></tbody></table>

### ❓ FAQ

#### 1\. We're a PMC-run project with client sign-off — which workflow?

**Workflow 6** — RFI Initiator (Contractor) raises the RFI, Checker (PMC) inspects, Approver (Client) signs off (L1). Add more levels (Workflow 7 or 8) if you need Site Engineer or PMC Manager sign-offs before the client.

#### 2\. Our contractor self-certifies before we inspect — how do we set that up?

Use an **RFI Approval** workflow (e.g. **Workflow 10**): the **Maker QC (Contractor's QC)** clears the RFI **before** the Checker (PMC) is called.

#### 3\. We don't want any RFI — can the Checker just inspect?

Yes — **Workflows 1–4** have **no RFI**; the Checker (PMC) inspects directly, with 0 to 3 sign-offs afterwards.

#### 4\. What is Re-RFI On vs Off in practice?

On a **Redo after inspection**: **Off** sends the work back to the **checklist stage** (the Checker re-inspects directly); **On** makes the RFI Initiator **raise a fresh RFI** first. On is more formal and accountable.

#### 5\. What happens when an approver gives a Redo?

The work goes back for re-inspection. With **Re-RFI Off** it returns to the **checklist stage** (Checker re-inspects, no fresh RFI); with **Re-RFI On** the RFI Initiator **raises a fresh RFI** first. After it passes again, the **approval cycle restarts from L1.**

#### 6\. What happens if the RFI is rejected?

If the RFI is **rejected before inspection starts**, you **start again from the RFI** (raise a fresh RFI) — whatever the Re-RFI setting — because the checklist stage never began.

#### 7\. What happens if the inspection fails?

Only the **failed checkpoints** are re-inspected — though you also have the **option to change other checkpoints** if needed.

#### 8\. How many approval levels can I have?

Up to **three** (L1 → L2 → L3), applied **in sequence** — e.g. Site Engineer, PMC Manager, Client.

#### 9\. Can each stage use a different workflow?

Yes — every stage (Pre / During / Post) can have its **own** workflow.

#### 10\. Who sets up the workflow?

Decide the steps and levels you need, then **contact the digiQC team** to configure it.

### 💡 Good to know

-   Workflows are configured **per stage** — each can differ, and completing one **unlocks the next.**
    
-   Approvals are **sequential**, and a **Redo restarts the approval cycle from L1.**
    
-   A **Redo** restarts from the **checklist stage** (Re-RFI Off) or a **fresh RFI** (Re-RFI On); a **rejected RFI** restarts from the **RFI** because inspection never began.
    
-   An **inspection fail** re-inspects only the failed checkpoints, with the **option to change others.**
    
-   There are **20 combinations** across three groups — No RFI, RFI (Re-RFI Off), RFI (Re-RFI On). Contact the **digiQC team** to configure yours.
    

### 🔗 Related articles

-   2.2.7 RFI process and inspection
    
-   2.2.8 RFI process without Approver
    
-   2.2.9 RFI process with Approver
    
-   2.2.6 How to "PASS" the Approved inspection to complete the stage?