# 2.2.14 Re-inspect fail checklist

A failed inspection sits in the Available tab with a Fail tag on the top-right of its card. Tap the card to open it, change all the failed checkpoints (tap Show all points to see the rest), then Pass or Seek approval — all failed checkpoints must be changed first.

### Overview

When a checklist stage is marked **Failed**, it stays in the **Available** tab with a **"Fail" tag** on its card. You open it and **change all the failed checkpoints**, then **Pass** or **Seek approval**.

### 🧭 How to use

1.  Open Inspect and go to the **Available** tab. **Select the project.**
    
2.  Find the **failed inspection** — its card shows a **"Fail" tag on the top-right corner.**
    
3.  **Tap the card** to open the failed inspection.
    
4.  **Change / answer all the failed checkpoints**, one by one. _(To review the points that passed, tap "Show all points".)_
    
5.  At the bottom, choose **Pass** (to mark it passed) or **Seek approval** (to send it for approval), per the stage's process. **All failed checkpoints must be changed before Pass / Seek approval is available.**
    
6.  Select the **Team**, set a **reminder** if needed, and tap **Done.**
    
7.  If there's a **next stage**, tap **"Go to inspection list"** to head to the **Available** tab and continue.
    

### ❓ FAQ

#### 1\. Where do I find a failed inspection?

In the **Available** tab — the failed inspection's card carries a **"Fail" tag on the top-right corner.** Tap the card to open it.

#### 2\. Do I have to re-inspect the whole checklist?

No — only the **failed checkpoints** need changing. To review the points that already passed, tap **"Show all points".**

#### 3\. Why can't I Pass or Seek approval yet?

Because **all the failed checkpoints must be changed first.** Once every failed point is addressed, **Pass / Seek approval** becomes available.

#### 4\. What happens if there's a next stage?

Tap **"Go to inspection list"** — you'll go to the **Available** tab to continue with the next stage.

### 💡 Good to know

-   A **failed** inspection stays in the **Available** tab with a **"Fail" tag** on the top-right of its card.
    
-   **All failed checkpoints must be changed** to enable **Pass / Seek approval.**
    
-   **"Show all points"** reveals the checkpoints that already passed.
    
-   Set the **Team** and a **reminder** before tapping **Done.**
    

### 🔗 Related articles

-   2.2.15 Re-inspect redo checklist
    
-   2.2.5 Inspection list explanation - Available, Paused & Approval
    
-   2.2.6 How to "PASS" the Approved inspection to complete the stage?
    