description: "When an approver sends an inspection back for Redo, it sits in the Available tab with a Redo tag on its card. Tap the card, change all the redo points (tap Show all points for the rest), then Seek approval — because it came from an approver there is no Pass, only Seek approval, and all redo points must be changed first."
url: https://help.digiqc.com/en/articles/179-2215-re-inspect-redo-checklist
collection: "2.2 Inspect"
updated: 2026-11-05
language: en
---

# 2.2.15 Re-inspect redo checklist

When an approver sends an inspection back for Redo, it sits in the Available tab with a Redo tag on its card. Tap the card, change all the redo points (tap Show all points for the rest), then Seek approval — because it came from an approver there is no Pass, only Seek approval, and all redo points must be changed first.

### Overview

When an **approver sends an inspection back for Redo**, it stays in the **Available** tab with a **"Redo" tag** on its card. You open it and **change all the redo points**, then **Seek approval** — because the redo came from an approver, it goes **back for approval** (there is **no Pass** option here).

### 🧭 How to use

1.  Open Inspect and go to the **Available** tab. **Select the project.**
    
2.  Find the **redo inspection** — its card shows a **"Redo" tag** on the top-right corner.
    
3.  **Tap the card** to open it.
    
4.  **Change / answer all the redo points**, one by one. _(To review the other points, tap "Show all points".)_
    
5.  At the bottom, tap **Seek approval.** Because the redo came from an **approver**, it must go **back for approval** — so only **Seek approval** appears (there is **no Pass**). **All redo points must be changed first.**
    
6.  Select the **Team** and the **approver to notify**, and tap **Done.**
    
7.  If there's a **next stage**, tap **"Go to inspection list"** to head to the **Available** tab and continue.
    

### ❓ FAQ

#### 1\. Why is there no "Pass" option for a redo?

Because a redo **came from an approver** — it must go **back for approval.** So only **Seek approval** is available, not Pass.

#### 2\. Where do I find a redo inspection?

In the **Available** tab — its card carries a **"Redo" tag** on the top-right corner. Tap the card to open it.

#### 3\. Do I have to redo the whole checklist?

No — only the **redo points** need changing. To review the other points, tap **"Show all points".**

#### 4\. Why can't I Seek approval yet?

Because **all the redo points must be changed first.** Once every redo point is addressed, **Seek approval** becomes available.

#### 5\. What's the difference between a Fail and a Redo?

A **Fail** happens **during inspection** — depending on the stage you can Pass it or Seek approval. A **Redo** is sent **by an approver**, so it can only be **Sent for approval** again (see _2.2.14 Re-inspect fail checklist_).

#### 6\. What happens if there's a next stage?

Tap **"Go to inspection list"** — you'll go to the **Available** tab to continue.

### 💡 Good to know

-   A **redo** inspection stays in the **Available** tab with a **"Redo" tag** on its card.
    
-   Because it came from an **approver**, only **Seek approval** is available — **no Pass.**
    
-   **All redo points must be changed** to enable **Seek approval.**
    
-   **"Show all points"** reveals the other checkpoints.
    
-   Select the **Team** and **approver to notify** before tapping **Done.**
    

### 🔗 Related articles

-   2.2.14 Re-inspect fail checklist
    
-   2.2.5 Inspection list explanation - Available, Paused & Approval
    
-   2.2.6 How to "PASS" the Approved inspection to complete the stage?
    
-   2.2.13 digiQC Inspection Workflows