2.2.8 RFI process without Approver

When your setup allows raising an RFI directly (no approval needed), fill in the checklist and tap Raise RFI, then select the team and Checker(s) to notify and set the mandatory Inspection request on date and time. The notified Checker is alerted to carry out the inspection.

Overview

Some setups let you raise an RFI (Request for Inspection) directly, without it needing an approver. You fill in the checklist and Raise RFI, then choose which Checker(s) to notify — they get an alert to carry out the inspection. This guide shows that flow.

🧭 How to use

  1. Open Inspect and select/switch the project from the top.

  2. Tap + Add, select the checklist, and enter the location — type it manually, or pick a predefined location from Nomenclature and add a custom name. Then tap Raise RFI (top-right).

  3. Select the witness and add photos; add drawings if they are mandatory. Then answer all the checkpoints. To record extra observations, tap the + (additional point) button.

  4. Tap Raise RFI, then: select the Team to notify, select the Checker(s) to notify, set the "Inspection request on" date and time (mandatory), and tap DONE.

  5. The RFI syncs automatically (shown at the top). The selected Checker then receives a notification to initiate the next stage and conduct the inspection.

❓ FAQ

1. What does "RFI without approver" mean?

It's a setup where you can raise the RFI directly, without an approval step. The RFI goes straight to notifying the Checker(s) you select.

2. How is this different from RFI with an approver?

Without an approver there is no review/accept step — you raise the RFI and the Checkers are notified directly. (With an approver, the RFI is reviewed and accepted first — see 2.2.9 RFI process with Approver.)

3. Can I add extra points while raising an RFI?

Yes — on the checkpoints screen, tap the + (additional point) button to add your own points.

4. What is the "Inspection request on" date and time?

It's when you are requesting the inspection to be carried out. You set the date and time while raising the RFI — this is mandatory — and the notified Checker is alerted for it.

5. Who carries out the inspection after the RFI is raised?

The Checker you selected to notify receives an alert to initiate the next stage and conduct the inspection.

6. Do I have to sync it manually?

No. The RFI syncs automatically — you'll see it syncing at the top.

💡 Good to know

  • This flow is available only when the setup allows raising an RFI directly (no approval needed).

  • You fill in the full checklist (witness, drawings if mandatory, all checkpoints) before raising the RFI.

  • While raising the RFI you choose the team and Checker(s) to notify and set the "Inspection request on" date and time — this date/time is mandatory.

  • The notified Checker gets a notification to carry out the inspection.

🔗 Related articles

  • 2.2.7 RFI process and inspection

  • 2.2.9 RFI process with Approver

  • 2.2.1 How to start an inspection?

  • 2.2.10 Choosing a location: levels, your own name, or both

क्या इससे आपके सवाल का जवाब मिला?
😞
😐
😁