What is RFI (Request for Inspection)?

RFI (Request For Inspection) in digiQC is the step where the contractor/maker requests an inspection, telling the checker the work is ready. With RFI on, the contractor raises the RFI, the checker inspects; if an approver is set the RFI is reviewed first. Can run with/without approver; Re-RFI on Fail/Redo/Reject; numbers can be auto-generated.

Answer

RFI stands for Request For Inspection. In digiQC, it's the step where the person who did the work (the contractor / maker) formally requests an inspection — telling the checker (the PMC or QC engineer) that the work is ready to be inspected.

When RFI is turned on for a checklist stage:

  • The contractor raises the RFI once the work is ready.

  • The checker is notified and then carries out the inspection against the checklist.

  • If an approver is set, the RFI is first reviewed (accepted or rejected) before the inspection begins.

This keeps a clear record of who requested the inspection and when, so work is only checked once it's actually ready.

Good to know

  • RFI can run with or without an approver.

  • On a Fail / Redo / Reject, a new RFI (Re-RFI) can be raised for the same stage.

  • RFI numbers can be auto-generated (RFI Number Configurator).

🔗 Learn more

  • 2.5.25 RFI Introduction and setup for the Project

  • 2.5.26 Setup RFI stage for Project Checklist

  • 2.5.28 All Inspection workflows with RFI

Still stuck?

If you'd like help setting up RFI, message us on WhatsApp chat (+91 6353450480) or check help.digiqc.com.

Did this answer your question?
😞
😐
😁