Can a contractor request an inspection (RFI)?

Yes. With RFI enabled on a checklist stage, the contractor (maker) raises a Request For Inspection when work is ready; the checker is notified and inspects only after that request. An RFI approver and Re-RFI (a fresh RFI after a fail) can also be configured. H

Answer

Yes. With RFI enabled on a checklist stage, the contractor (maker) raises a Request For Inspection when work is ready; the checker is notified and inspects only after that request. An RFI approver and Re-RFI (a fresh RFI after a fail) can also be configured. How to set it up: turn on RFI for the project, then enable it on the relevant checklist stage.

Still stuck?

If you would like to see it in your setup, message us on WhatsApp chat (+91 6353450480) or check help.digiqc.com.